ROUTE 2 PROJECT WEBSITE

This website has been created to streamline the transfer of key project information from the project management team to the employee-owners building the project.

Here, you can view project plans, specs, productions, schedules, wage orders, etc.  The goal is to provide all necessary documents & project plans in one easy to access location.  

You can subscribe below to get project updates sent directly to you.

project info

  • Paving Pic 1.jpg
  • Paving Pic 3.jpg
  • Paving Pic 4.jpg
  • Paving Pic 8.jpg
  • Paving Pic 10.jpg
  • I-35.jpg
  • IMG_2379.jpg
  • mill.jpg
  • morse mill.jpg
  • night mill.jpg
  • paving.JPG
Missouri Dept. of Transportation

*Click icons to view*

The Missouri Department of Transportation (MoDOT) has contracted Emery Sapp & Sons to complete Project JKU0049. This project consists of resurfacing approximately 14.7 miles of Route 2, extending from Independence Street in Harrisonville to Route ZZ in La Tour, MO, spanning both Cass County and Johnson County.

Total(s):
-Asphalt: 22,833ton
-Milling: 2,659sy
-Edge Rock: 7,497ton
-Tack: 38,100gal
-Total Miles: 14.66
(Lane Miles: 29.31)
Shifts:
-Shift Type: DAY
-Daily Shift Hours: 12
-Daily End: 6:30pm
-Daily Start: 6:30am
-Days: Mon - Thu
-Estimated Days: 20

ROUTE 2 (Cass & Johnson County) // ESS Project Number: 1625132 // Modot Project Number: JKU0049 // Modot Contract ID: 250815-C03 //

Daily Productions:
-0.5": 1,630 ton/day
-1": 2,174 ton/day
-Milling: 1,772 sy/day
- Daily Tack: 3,287gal
-Edge Rock: 1,249sy
-Daily Lane Miles: 4.89

MoDOT OFFICIAL Website
 

Missouri Dept. of Transportation

Other ESS Links:
 

PROJECT UPDATES

 

DATE: April 23rd, 2026

SCHEDULE UPDATE: MILLING

SCHEDULE UPDATE: Due to scheduling adjustments, Emery Sapp & Sons will begin preliminary roadway milling operations along Route 2 on Tuesday, April 28, 2026.

 

Milling activities will include curb milling along S. Independence Street to the intersections of W. South Street and Route 2. Crews will also perform depth transition cuts at all side streets, entrances, and concrete/asphalt driveways. These transitions are necessary to provide a smooth and consistent connection between existing pavement and the new roadway surface.

 

Motorists are advised to use caution, remain alert for workers, and follow all posted flagger instructions while traveling through the work zone.

 

Work is anticipated to take approximately 1.5 days and will begin after 8:00 a.m. each day to minimize impacts to morning traffic.

 

The paving schedule remains on track to begin May 4, weather permitting.

 

DATE: April 20th, 2026

Road Closure Notice(s)

Emery Sapp & Sons will have employee-owners distributing Road Closure Notices throughout Harrisonville neighborhoods on April 21, 2026. These notices will provide detailed information regarding upcoming access closures, traffic guidance, and instructions for navigating the work zone. A QR code linking directly to this project website will also be included for easy access to updates.

Construction activities remain on schedule, with paving operations in Harrisonville anticipated to begin on May 4, 2026, at 8am.

DATE: April 14th, 2026

Locates & Post Mount Sign Install

Subcontractor Streetwise will have locates done the week of April 13th to mark out post mounted traffic control signs. 

Streetwise will begin installing the post mounted traffic control signs along Route 2 from Harrisonville to La Tour the following week of April 20th in advance of construction starting.

DATE: April 14th, 2026

Asphalt Plant Update

Emery Sapp & Sons is in the process of erecting asphalt plant #10 at the Garden City plant site.  Construction is estimated to start on Monday May 4th.  

For the latest project insights and schedule changes, subscribe to our project updates emails group.

DATE: April 23rd, 2026

SCHEDULE UPDATE: MILLING

SCHEDULE UPDATE: Due to scheduling adjustments, Emery Sapp & Sons will begin preliminary roadway milling operations along Route 2 on Tuesday, April 28, 2026.

 

Milling activities will include curb milling along S. Independence Street to the intersections of W. South Street and Route 2. Crews will also perform depth transition cuts at all side streets, entrances, and concrete/asphalt driveways. These transitions are necessary to provide a smooth and consistent connection between existing pavement and the new roadway surface.

 

Motorists are advised to use caution, remain alert for workers, and follow all posted flagger instructions while traveling through the work zone.

 

Work is anticipated to take approximately 2–3 days and will begin after 8:00 a.m. each day to minimize impacts to morning traffic.

 

The paving schedule remains on track to begin May 4, weather permitting.

 

Emery Sapp & Sons appreciates the public’s cooperation and is committed to maintaining a safe and efficient work zone for all.

get project updates:

Stay informed with the latest construction updates, project schedules, and traffic control information directly in your inbox. Notifications will be sent out a couple of days in advance of work starting, with updates of locations & times, as the project progresses.

** Email information will not be kept or handed out. The ONLY purpose of this site is to inform the public of project happenings **